| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1 | TRAZO Y NIVELACION DEL TERRENO, INC. COLOCACION DE MOJONERAS, BANDERAS, ESTACAS, BANCOS DE NIVEL, PUNTOS DE REFERENCIA. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CALHIDRA02 | CALHIDRA EN SACO | ton | 0.000200 | $1,100.00 | $0.22 |
| CALHIDRA02 | CALHIDRA EN SACO | ton | 0.000200 | $1,100.00 | $0.22 |
| CALHIDRA02 | CALHIDRA EN SACO | ton | 0.000200 | $1,100.00 | $0.22 |
| CALHIDRA02 | CALHIDRA EN SACO | ton | 0.000200 | $1,100.00 | $0.22 |
| MADERA DE PINO 3A | madera para estacas | pt | 0.150000 | $4.34 | $0.65 |
| MADERA DE PINO 3A | madera para estacas | pt | 0.150000 | $4.34 | $0.65 |
| MADERA DE PINO 3A | madera para estacas | pt | 0.150000 | $4.34 | $0.65 |
| MADERA DE PINO 3A | madera para estacas | pt | 0.150000 | $4.34 | $0.65 |
| PINTURA ESMALTE COME | PINTURA ESMALTE | LT | 0.003500 | $58.45 | $0.20 |
| PINTURA ESMALTE COME | PINTURA ESMALTE | LT | 0.003500 | $58.45 | $0.20 |
| PINTURA ESMALTE COME | PINTURA ESMALTE | LT | 0.003500 | $58.45 | $0.20 |
| PINTURA ESMALTE COME | PINTURA ESMALTE | LT | 0.003500 | $58.45 | $0.20 |
| Suma de Material | $4.30 | ||||
| Mano de Obra | |||||
| CUA TOPOGRAFO 2 | (1 topografo + 2 cadeneros) | JOR | 0.002500 | $1,506.52 | $3.77 |
| CUA TOPOGRAFO 2 | (1 topografo + 2 cadeneros) | JOR | 0.002500 | $1,506.52 | $3.77 |
| CUA TOPOGRAFO 2 | (1 topografo + 2 cadeneros) | JOR | 0.002500 | $1,506.52 | $3.77 |
| CUA TOPOGRAFO 2 | (1 topografo + 2 cadeneros) | JOR | 0.002500 | $1,506.52 | $3.77 |
| Suma de Mano de Obra | $15.07 | ||||
| Equipo | |||||
| ATRANSITO | TRANSITO CON TRIPIE Y PLOMADA OPTICA | hora | 0.010000 | $10.64 | $0.11 |
| ATRANSITO | TRANSITO CON TRIPIE Y PLOMADA OPTICA | hora | 0.010000 | $10.64 | $0.11 |
| ATRANSITO | TRANSITO CON TRIPIE Y PLOMADA OPTICA | hora | 0.010000 | $10.64 | $0.11 |
| ATRANSITO | TRANSITO CON TRIPIE Y PLOMADA OPTICA | hora | 0.010000 | $10.64 | $0.11 |
| ANIVEL CON TRIPIE | NIVEL CON TRIPIE | HR | 0.075000 | $23.77 | $1.78 |
| ANIVEL CON TRIPIE | NIVEL CON TRIPIE | HR | 0.075000 | $23.77 | $1.78 |
| ANIVEL CON TRIPIE | NIVEL CON TRIPIE | HR | 0.075000 | $23.77 | $1.78 |
| ANIVEL CON TRIPIE | NIVEL CON TRIPIE | HR | 0.075000 | $23.77 | $1.78 |
| Suma de Equipo | $7.56 | ||||
| Auxiliar | |||||
| CONCRETO F-C=100 H/O | CONCRETO HECHO EN OBRA F'c = 100 KG/CM2 AGREGADO MAX. 3/4" R.N. | M3 | 0.000700 | $840.76 | $0.59 |
| CONCRETO F-C=100 H/O | CONCRETO HECHO EN OBRA F'c = 100 KG/CM2 AGREGADO MAX. 3/4" R.N. | M3 | 0.000700 | $840.76 | $0.59 |
| CONCRETO F-C=100 H/O | CONCRETO HECHO EN OBRA F'c = 100 KG/CM2 AGREGADO MAX. 3/4" R.N. | M3 | 0.000700 | $840.76 | $0.59 |
| CONCRETO F-C=100 H/O | CONCRETO HECHO EN OBRA F'c = 100 KG/CM2 AGREGADO MAX. 3/4" R.N. | M3 | 0.000700 | $840.76 | $0.59 |
| Suma de Auxiliar | $2.35 | ||||
| Costo Directo | $29.28 |