| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 42 | PISO DE CONCRETO PREMEZCLADO F'C= 175 KG/CM2 TMA 3/4" DE 10 CM DE ESPESOR, ARMADO CON VRS # 3 @ 25 CM EN AMBOS LADOS, ACABADO ESCOBILLADO FINO, INCLUYE: ARMADO, CIMBRADO, COLADO, CURADO. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC PREMEZ 175 | concreto premezclado fc=175 KG/CM2 | m3 | 0.105000 | $790.00 | $82.95 |
| FIBRA FEST | FIBRA DE POLIPROPILENO PARA CONCRETO | kg | 0.150000 | $71.25 | $10.69 |
| MEMBRANA DE PARAF. | tela prs plicout | M2 | 0.300000 | $14.25 | $4.28 |
| CIMBRA METALICA | CIMBRA METALICA(CANAL MONTEN) | ML | 0.150000 | $7.25 | $1.09 |
| AGUA | AGUA | M3 | 0.005000 | $40.00 | $0.20 |
| MALLA 6-6 8/8M2 | MALLA ELECTROSOLDADA 6/6 8/8 | M2 | 1.100000 | $19.50 | $21.45 |
| Suma de Material | $120.65 | ||||
| Mano de Obra | |||||
| C02-0450 | CUAD. No 45 ( 1 ALBAÑIL + 5 PEONES ) | JOR | 0.022222 | $2,135.21 | $47.45 |
| Suma de Mano de Obra | $47.45 | ||||
| Equipo | |||||
| AREGLA VIBRATORIA | REGLA VIBRATORIA | hora | 0.010000 | $210.67 | $2.11 |
| API-ALLANADORA MEC | ALLANADORA MECANICA CON ASPAS | hora | 0.025000 | $40.19 | $1.00 |
| Suma de Equipo | $3.11 | ||||
| Costo Directo | $171.21 |