| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1- | PLANTILLA DE CONCRETO F'C= 100 KG/CM2 DE 5 CMS DE ESPESOR. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA PINO BARROTE | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 0.500000 | $8.50 | $4.25 |
| CLAVO (VARIAS MED.) | CLAVO PARA MADERA VARIAS MEDIDAS | KG | 0.020000 | $25.00 | $0.50 |
| ALAMBRE REC | ALAMBRE RECOCIDO CAL. 16 | KG | 0.100000 | $15.00 | $1.50 |
| CONCRETO PRE F´C100 | CONCRETO PREMEZCLADO DE F´C=100 KG/CM2 | M3 | 0.055000 | $850.00 | $46.75 |
| REVENIMIENTO | REVENIMIENTO PARA BOMBEO | M3 | 0.055000 | $130.00 | $7.15 |
| BOMBEO CONC | bombeo de concreto con sistema estacionario o pluma elevada | m3 | 0.055000 | $160.00 | $8.80 |
| Suma de Material | $68.95 | ||||
| Mano de Obra | |||||
| CUA ALBAÑIL 2 | ( 1 ALBAÑIL + 2 PEONES ) | JOR | 0.025000 | $1,499.80 | $37.50 |
| Suma de Mano de Obra | $37.50 | ||||
| Costo Directo | $106.45 |