| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 9, | DALA DE 15 X 20 CMS DE CONCRETO F'C= 200 KG/CM2. INCLUYE: VR. #3 ANCLADA DE 25 CMS DE LARGO @ 30 CMS, MÁS 1 VR. #3 A TODO LO LARGO. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRA 2 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 2.500000 | $14.00 | $35.00 |
| CLAVO (VARIAS MED.) | CLAVO PARA MADERA VARIAS MEDIDAS | KG | 0.250000 | $25.00 | $6.25 |
| ACEITE | Aceite para motores diesel | lt | 0.050000 | $35.00 | $1.75 |
| CONCRETO PREM 200 | CONCRETO PREMEZCLADO FC=200 KG/CM2 | m3 | 0.033000 | $950.00 | $31.35 |
| Suma de Material | $74.35 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 10 | (1 OF. CARPINTERO DE OBRA NEGRA + 2 AYUDANTES ) | JOR | 0.033333 | $1,615.49 | $53.85 |
| Suma de Mano de Obra | $53.85 | ||||
| Auxiliar | |||||
| ACERO NO. 3 - 8 | ACERO DE REFUERZO DEL No. 3 AL No.8 | kg | 3.000000 | $18.43 | $55.29 |
| Suma de Auxiliar | $55.29 | ||||
| Costo Directo | $183.49 |