| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2.18.1 | 100 x 100 x 100 cm. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO PRE-250 | CONCRETO PREMEZCLADO DE F'C= 250 KG/CM2, ELABORADO CON CEMENTO CPO-30-RS | M3 | 1.144000 | $852.00 | $974.69 |
| ANGULO 1 3/4 X 3/16 | ANGULO DE ACERO DE 1 3/4 X 3/16" | KG | 17.850000 | $9.02 | $161.01 |
| ANGULO 1 1/2 X 3/16 | ANGULO DE ACERO DE 1 1/2" X 3/16" | KG | 13.400000 | $9.02 | $120.87 |
| SOLDADURA | SOLDADURA E 7018 | KG | 0.060000 | $33.03 | $1.98 |
| Suma de Material | $1,258.54 | ||||
| Mano de Obra | |||||
| CUAD OC 12 | (1 Of. Albanil + 1 Peón) | JOR | 0.500000 | $733.01 | $366.51 |
| CUAD OC 08 | CUAD. 1.00 HOJALTERO/HERRERO + 1.00 AYUDANTE GENERAL. | JOR | 0.055556 | $681.46 | $37.86 |
| Suma de Mano de Obra | $404.36 | ||||
| Equipo | |||||
| AAESMERILADORA | Esmeriladora | HR | 0.130390 | $8.89 | $1.16 |
| AAMAQUINARIA-94 | Soldadora Miller Dimension Mod. 652 | HR | 0.145760 | $29.02 | $4.23 |
| Suma de Equipo | $5.39 | ||||
| Auxiliar | |||||
| 03-2121 | ACERO DE REFUERZO VARIOS DIAMETROS. | KG | 59.660000 | $12.11 | $722.48 |
| Suma de Auxiliar | $722.48 | ||||
| Concepto | |||||
| CE-02-01 | CIMBRA COMUN | M2 | 10.760000 | $165.07 | $1,776.15 |
| Suma de Concepto | $1,776.15 | ||||
| Costo Directo | $4,166.93 |