| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 047Y17C02D5 | De 152 x 360 cm, con un tablero | pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| SEÑAL INFORMATIVA-13 | SID-13 BANDERA SEÑAL INFORMATIVA DE IDENTIFICACION DE 152 * 366 CM | PZA | 1.000000 | $10,590.00 | $10,590.00 |
| CONCRETO PRE-05 | CONCRETO PREMEZCLADO DE F'C= 250 KG/CM2, ELABORADO CON CEMENTO CPO-30-RS | M3 | 4.700000 | $790.00 | $3,713.00 |
| ACERO | ACERO REF.VAR.DIAM. | kg | 431.770000 | $7.57 | $3,268.50 |
| GALVANIZADO EN CAL. | GALVANIZADO EN CALIENTE INCLUYE FLETE A LA OBRA | KG | 431.770000 | $5.50 | $2,374.74 |
| Suma de Material | $19,946.23 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 10 | (1 Of. Albanil + 5 Peones). | JOR | 3.000000 | $1,805.92 | $5,417.76 |
| Suma de Mano de Obra | $5,417.76 | ||||
| Auxiliar | |||||
| HA101 | Plantilla concreto f'c=100 kg/cm2 de 5 cm. | m2 | 8.410000 | $62.75 | $527.73 |
| CIMBRA EN CIMEN | CIMBRA COMUN EN CIMENTACION | M2 | 10.800000 | $154.66 | $1,670.33 |
| Suma de Auxiliar | $2,198.06 | ||||
| Costo Directo | $27,562.05 |