| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2.1 2 | ZAPATA DE CIMENTACION CORRIDA (Z2) INCLUYE CIMBRA Y DESCIMBRA ANCHO=80 CM PERALTE=15 CM ACERO DE REFUERZO FY'=4200 KG/CM2, ARMADA CON VARILLAS DEL No. 3 @ 20 CMS EN SENTIDO TRANVERSAL Y 4 VARILLAS No. 3 EN SENTIDO LONGITUDINAL GALV. POR INMERSION EN CALIENTE.CONCRETO F'C=250 KG/CM2-3/4" PREMEZCLADO, BOMBEADO, VIBRADO Y CURADO | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| GALVANIZADO POR INME | KG | 7.830000 | $3.00 | $23.49 | |
| AGUA | M3 | 0.057000 | $45.00 | $2.57 | |
| BOMBEO | BOMBEO DE CONCRETO | M3 | 0.126000 | $110.00 | $13.86 |
| Suma de Material | $39.92 | ||||
| Concepto | |||||
| CE-02-01 | CIMBRA COMUN | M2 | 0.300000 | $72.29 | $21.69 |
| CE-03-03 | ACERO DE REFUERZO DEL No. 5 EN CIMENTACION | TON | 0.008000 | $13,029.10 | $104.23 |
| CE-05-02 | F'c= 250 KG/CM2, AGREGADO MAXIMO DE 19 MM., CLASE I | M3 | 0.126000 | $1,181.25 | $148.84 |
| Suma de Concepto | $274.76 | ||||
| Costo Directo | $314.67 |