| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2.1 15 | FIRME DE CONCRETO F´c=150 KG/CM2 PREMEZCLADO, VIBRADO Y CURADO REFORZADO CON MALLA 6*6/10*10 GALV. POR IMNERSION EN CALIENTE DE 8 CMS DE ESP. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=150 H/O | CONCRETO F'c=150 KG/CM2, HECHO EN OBRA AGREGADO MAXIMO GRAVILLA 3/4" | M3 | 0.084000 | $781.40 | $65.64 |
| MALLA 6X6 10X10 | M2 | 1.100000 | $13.00 | $14.30 | |
| CALZAS P/MALLA-ACERO | Calzas para malla o acero en pisos | PZA | 2.000000 | $0.95 | $1.90 |
| AGUA | M3 | 0.067000 | $45.00 | $3.02 | |
| MADERA-2 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 1.060000 | $5.90 | $6.25 |
| CLAVO | CLAVO | KG | 0.040000 | $13.50 | $0.54 |
| GALVANIZADO DE MALLA | GALVANIZADO DE MALLA | KG | 1.387100 | $4.00 | $5.55 |
| Suma de Material | $97.20 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-02 | (1 ALBAÑIL + 1 AYUDANTE DE ALBAÑIL) | JOR | 0.043480 | $576.23 | $25.05 |
| Suma de Mano de Obra | $25.05 | ||||
| Costo Directo | $122.25 |