| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 3.5.13.1 | SARDINEL DE CONCRETO F'c= 150 KG/CM2 SIMPLE DE 10 X 10 CMS FORRADO DE AZULEJO ANTIDERRAPANTE DE 20X 20 CM CON CORTE 45o | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=150 H/O | CONCRETO F'c=150 KG/CM2, HECHO EN OBRA AGREGADO MAXIMO GRAVILLA 3/4" | M3 | 0.011000 | $781.40 | $8.60 |
| AZULEJO | M2 | 0.400000 | $90.00 | $36.00 | |
| ADHESIVO PARA LOSETA | ADHESIVO PARA LOSETA GRIS NORMAL (SACO 20 KG) | saco | 0.185000 | $58.59 | $10.84 |
| Suma de Material | $55.43 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-02 | (1 ALBAÑIL + 1 AYUDANTE DE ALBAÑIL) | JOR | 0.560000 | $576.23 | $322.69 |
| Suma de Mano de Obra | $322.69 | ||||
| Costo Directo | $378.12 |