| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2.1 6 | CONTRATRABE DE CIMENTACION (TC3) INCLUYE CIMBRA Y DESCIMBRA SECCION 0.20 X 0.40 M REFORZADO CON 4 VARILLAS DE #4 Y EST. # 2 @ 20 CMS. GALVANIZADO POR INMERSION EN CALIENTE CONCRETO F'C=250 KG/CM2-3/4" PREMEZCLADO, BOMBEADO, VIBRADO Y CURADO | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| GALVANIZADO POR INME | KG | 7.800000 | $3.00 | $23.40 | |
| AGUA | M3 | 0.600000 | $45.00 | $27.00 | |
| Suma de Material | $50.40 | ||||
| Concepto | |||||
| CE-02-01 | CIMBRA COMUN | M2 | 0.800000 | $72.29 | $57.83 |
| CE-03-03 | ACERO DE REFUERZO DEL No. 5 EN CIMENTACION | TON | 0.008000 | $13,029.10 | $104.23 |
| CE-05-02 | F'c= 250 KG/CM2, AGREGADO MAXIMO DE 19 MM., CLASE I | M3 | 0.084000 | $1,181.25 | $99.23 |
| Suma de Concepto | $261.29 | ||||
| Costo Directo | $311.69 |