| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2.2.1 18 | TRABE EN ESTRUCTURA (T6) SECCION = 20 X 70 CM CIMBRA APARENTE REFORZADA CON 6 VARILLAS DEL #5, 4 ADIC. #3 Y EST. # 3 @ 20 CMS. DE ACERO GALVANIZADA EN INMERSION CALIENTE FY'=4200 KG/CM2 CONCRETO F'C=250 KG/CM2-3/4" | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO | ACERO REF.VAR.DIAM. | KG | 17.160000 | $9.40 | $161.30 |
| MADERA-2 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 5.480000 | $5.90 | $32.33 |
| DIESEL | DIESEL | LT | 0.258500 | $4.20 | $1.09 |
| ALAMBRE 16 MM | ALAMBRE GALVANIZADO | KG | 0.200000 | $16.95 | $3.39 |
| CIMBRAPLAY 6 MM | CIMBRAPLAY 6 MM | m2 | 0.000000 | $43.75 | $0.00 |
| GALVANIZADO POR INME | KG | 0.000000 | $3.00 | $0.00 | |
| CONCRETO DE 250 | CONCRETO PREMEZCLADO BOMBEABLE DE 250 KG/CM2, INCLUYE: CONCRETO CPO, REVENIMIENTO 12-14. | M3 | 0.108000 | $949.00 | $102.49 |
| CLAVO | CLAVO | KG | 0.300000 | $13.50 | $4.05 |
| CIMBRAPLAY 6 MM | CIMBRAPLAY 6 MM | m2 | 0.100000 | $43.75 | $4.38 |
| GALVANIZADO POR INME | KG | 11.370000 | $3.00 | $34.11 | |
| Suma de Material | $343.14 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-02 | (1 ALBAÑIL + 1 AYUDANTE DE ALBAÑIL) | JOR | 0.125000 | $576.23 | $72.03 |
| Suma de Mano de Obra | $72.03 | ||||
| Herramienta | |||||
| ANDAMIO METALICO | HASTA UNA ALTURA DE 6.00 M | R/DIA | 0.100000 | $45.00 | $4.50 |
| Suma de Herramienta | $4.50 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | hora | 0.033000 | $16.88 | $0.56 |
| Suma de Equipo | $0.56 | ||||
| Costo Directo | $420.22 |