| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2.2.1.12 | NERVADURA EN ESTRUCTURA N-1 LONGITUDINAL SECCION = 10 X25 CM REFORZADA CON 2 VAR. #3 Y EST. #2 @ 20 CMS, DE ACERO FY'=4200 KG/CM2 GALV. POR INMERSION EN CALIENTE CONCRETO PREMEZCLADO F'C=250 KG/CM2-3/4" BOMBEADO Y VIBRADO CON ACELERANTE. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO DE 250 | CONCRETO PREMEZCLADO BOMBEABLE DE 250 KG/CM2, INCLUYE: CONCRETO CPO, REVENIMIENTO 12-14. | M3 | 0.031000 | $949.00 | $29.42 |
| BOMBEO | BOMBEO DE CONCRETO | M3 | 0.031000 | $110.00 | $3.41 |
| ACELERANTE | ACELERANTE PARA CONCRETO | LT | 1.000000 | $30.00 | $30.00 |
| ACERO | ACERO REF.VAR.DIAM. | KG | 2.120000 | $9.40 | $19.93 |
| ALAMBRE 16 MM | ALAMBRE GALVANIZADO | KG | 0.300000 | $16.95 | $5.09 |
| GALVANIZADO POR INME | KG | 2.200000 | $3.00 | $6.60 | |
| Suma de Material | $94.44 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-02 | (1 ALBAÑIL + 1 AYUDANTE DE ALBAÑIL) | JOR | 0.083330 | $576.23 | $48.02 |
| Suma de Mano de Obra | $48.02 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | hora | 0.070000 | $16.88 | $1.18 |
| Suma de Equipo | $1.18 | ||||
| Costo Directo | $143.64 |