| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 7:01(F) | ZAPATA DE CIMENTACION AISLADA ( Z-AH1) INCLUYE CIMBRA Y DESCIMBRA DE 200 X 200 CM PERALTE=30 ACERO FY'=4200 KG/CM2: 23.75 kg de var # 6, 11.66 kg de var # 5 y 10.35 kg x ml de var del # 3 GALVANIZADO POR INMERSION EN CALIENTE CONCRETO FC= 250'KG/CM2-3/4" PREMEZCLADO BOMBEADO Y VIBRADO | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| GALVANIZADO POR INME | KG | 47.840000 | $3.00 | $143.52 | |
| AGUA | M3 | 0.120000 | $45.00 | $5.40 | |
| BOMBEO | BOMBEO DE CONCRETO | M3 | 1.260000 | $110.00 | $138.60 |
| Suma de Material | $287.52 | ||||
| Concepto | |||||
| CE-02-01 | CIMBRA COMUN | M2 | 0.360000 | $72.29 | $26.02 |
| CE-03-03 | ACERO DE REFUERZO DEL No. 5 EN CIMENTACION | TON | 0.046000 | $13,029.10 | $599.34 |
| CE-05-02 | F'c= 250 KG/CM2, AGREGADO MAXIMO DE 19 MM., CLASE I | M3 | 1.260000 | $1,181.25 | $1,488.38 |
| Suma de Concepto | $2,113.74 | ||||
| Costo Directo | $2,401.26 |