| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2.2.1 21 | TRABE EN ESTRUCTURA (T9) SECCION = 20 X 70 CM CIMBRA APARENTA REFORZADA CON 9 VARILLAS DEL #5, 4 ADIC . #3 Y EST. # 3 @ 20 CMS. DE ACERO GALVANIZADA POR INMERSION EN CALIENTE FY'=4200 KG/CM2 CONCRETO F'C=250 KG/CM2-3/4" | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO DE 250 | CONCRETO PREMEZCLADO BOMBEABLE DE 250 KG/CM2, INCLUYE: CONCRETO CPO, REVENIMIENTO 12-14. | M3 | 0.144000 | $949.00 | $136.66 |
| ACERO | ACERO REF.VAR.DIAM. | KG | 24.310000 | $9.40 | $228.51 |
| MADERA-2 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 5.480000 | $5.90 | $32.33 |
| DIESEL | DIESEL | LT | 0.258500 | $4.20 | $1.09 |
| ALAMBRE 16 MM | ALAMBRE GALVANIZADO | KG | 0.223000 | $16.95 | $3.78 |
| CIMBRAPLAY 6 MM | CIMBRAPLAY 6 MM | m2 | 0.340000 | $43.75 | $14.88 |
| GALVANIZADO POR INME | KG | 25.100000 | $3.00 | $75.30 | |
| Suma de Material | $492.54 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-02 | (1 ALBAÑIL + 1 AYUDANTE DE ALBAÑIL) | JOR | 0.167000 | $576.23 | $96.23 |
| Suma de Mano de Obra | $96.23 | ||||
| Herramienta | |||||
| ANDAMIO METALICO | HASTA UNA ALTURA DE 6.00 M | R/DIA | 0.100000 | $45.00 | $4.50 |
| Suma de Herramienta | $4.50 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | hora | 0.033000 | $16.88 | $0.56 |
| Suma de Equipo | $0.56 | ||||
| Costo Directo | $593.83 |