| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 5.1.8 | MOSQUITERO DE TELA CON MARCO DE ALUMINIO DE 1" EN AREAS DE CELOSIA | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TELA MOSQUITERO | TELA MOSQUITERO | m2 | 1.050000 | $15.50 | $16.28 |
| ALUM-07-07 | BOLSA 3" NAT. | tramo | 0.409000 | $160.00 | $65.44 |
| ALUM-10-10 | JUNQUILLO P/ESCALON. 3" NAT. | tramo | 0.083000 | $70.95 | $5.89 |
| ALUM-11-11 | TAPA BOLSA 3" NAT. | tramo | 0.570000 | $130.20 | $74.21 |
| ALUM 24 | TUERCA DE 1/2" | pieza | 1.400000 | $0.89 | $1.25 |
| ALUM 25 | ROLDANA DE 1/2" | pieza | 1.400000 | $0.89 | $1.25 |
| ALUM 03 | PIJAS | pieza | 1.990000 | $0.79 | $1.57 |
| ALUM 06 | TORNILLO PARA FIJAR CANCEL | pieza | 1.990000 | $1.47 | $2.93 |
| ALUM 07 | TAQUETE PARA FIJAR CANCE | pieza | 1.990000 | $0.69 | $1.37 |
| ALUM 10 | SILICON | pieza | 0.350000 | $48.83 | $17.09 |
| Suma de Material | $187.27 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-09 | (1 ALUMINERO + 2 AYUDANTES) | jor | 0.080000 | $781.03 | $62.48 |
| Suma de Mano de Obra | $62.48 | ||||
| Equipo | |||||
| TALADRO HILTI TE-54 | TALADRO HILTI TE-54 | hora | 0.500000 | $8.63 | $4.32 |
| Suma de Equipo | $4.32 | ||||
| Costo Directo | $254.07 |