| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2.1.1 | ZAPATA DE CIMENTACION CORRIDA (Z1) INCLUYE CIMBRA Y DESCIMBRA COMÚN ANCHO=60 CM PERALTE=15 CM , ACERO FY'=4200 KG/CM2 2 VARILLAS DEL No. 3 EN SENTIDO LONGITUDINAL Y VARILLAS DEL No. 3 @ 20 CMS. TRANSVERSAL, GALVANIZADO POR INMERSION EN CALIENTE CONCRETO F'C=250KG/CM2-3/4" PREMEZCLADO, BOMBEADO Y VIBRADO | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| GALVANIZADO POR INME | KG | 5.543000 | $3.00 | $16.63 | |
| AGUA | M3 | 0.057000 | $45.00 | $2.57 | |
| Suma de Material | $19.19 | ||||
| Concepto | |||||
| CE-03-03 | ACERO DE REFUERZO DEL No. 5 EN CIMENTACION | TON | 0.006000 | $13,029.10 | $78.17 |
| CE-02-01 | CIMBRA COMUN | M2 | 0.300000 | $72.29 | $21.69 |
| CE-05-02 | F'c= 250 KG/CM2, AGREGADO MAXIMO DE 19 MM., CLASE I | M3 | 0.094500 | $1,181.25 | $111.63 |
| Suma de Concepto | $211.49 | ||||
| Costo Directo | $230.68 |