| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2.2.2. 3 | NERVADURA EN ESTRUCTURA (N1) INCLUYE CIMBRA Y DESCIMBRA SECCION = 10 X35 CM REFORZADA CON 2 VAR. #3 Y EST. # 2 @ 20 CMS DE ACERO FY'=4200 KG/CM2 CONCRETO PREMEZCLADO F'C=250 KG/CM2-3/4" BOMBEADO, VIBRADO Y CON ACELERANTE GALVANIZADO POR INMERSION EN CALIENTE | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO DE 250 | CONCRETO PREMEZCLADO BOMBEABLE DE 250 KG/CM2, INCLUYE: CONCRETO CPO, REVENIMIENTO 12-14. | M3 | 0.037000 | $949.00 | $35.11 |
| BOMBEO | BOMBEO DE CONCRETO | M3 | 0.037000 | $110.00 | $4.07 |
| ACERO | ACERO REF.VAR.DIAM. | KG | 3.320000 | $9.40 | $31.21 |
| ALAMBRE 16 MM | ALAMBRE GALVANIZADO | KG | 0.200000 | $16.95 | $3.39 |
| GALVANIZADO POR INME | KG | 3.450000 | $3.00 | $10.35 | |
| Suma de Material | $84.13 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-02 | (1 ALBAÑIL + 1 AYUDANTE DE ALBAÑIL) | JOR | 0.028570 | $576.23 | $16.46 |
| Suma de Mano de Obra | $16.46 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | hora | 0.060000 | $16.88 | $1.01 |
| Suma de Equipo | $1.01 | ||||
| Costo Directo | $101.61 |