| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 3.5.1 8 | REGISTRO TIPO, SECCION INT. 80 X 80 CMS HASTA 1.00 M DE PROF (SEGUN PROYECTO), CIMBRA Y DESCIMBRA APARENTE, REFORZADO CON VARILLAS DEL No 3 A CADA 20 CMS EN AMBOS SENTIDOS, CONCRETO F´c=200 kg/cm2 CON AGREG. MAX. 3/4# INC: GALVANIZADO POR INMERSION EN CALIENTE DEL ACERO, MATERIALES Y MANO DE OBRA. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=150 H/O | CONCRETO F'c=150 KG/CM2, HECHO EN OBRA AGREGADO MAXIMO GRAVILLA 3/4" | M3 | 0.065000 | $781.40 | $50.79 |
| CONCRETO F-C=100 H/O | CONCRETO HECHO EN OBRA F'c = 100 KG/CM2 AGREGADO MAX. 3/4" R.N. | m3 | 0.032000 | $668.10 | $21.38 |
| MARCO MET, P/REG. | DE 40 X 60 CMS. DE ANGULO DE 1 1/2" Y 1 1/4" EN 1/8" DE ESPESOR. | pieza | 1.000000 | $185.57 | $185.57 |
| TABIMAX | TABIQUE MARCA "TABIMAX" | PZA | 88.000000 | $2.05 | $180.40 |
| MORTERO CEM-ARE 1:5 | MORTERO CEMENTO ARENA 1:5 | m3 | 0.107000 | $566.33 | $60.60 |
| MADERA DE PINO | MADERA PINO 3a. | pt | 1.200000 | $5.90 | $7.08 |
| CLAVO | CLAVO | KG | 0.100000 | $13.50 | $1.35 |
| CIMBRAPLAY | CIMBRAPLAY 16 MM | m2 | 0.100000 | $69.00 | $6.90 |
| DESMOLDANTE | DESMOLDANTE SEPAROL DE SIKA | litro | 0.180000 | $9.76 | $1.76 |
| ACERO | ACERO REF.VAR.DIAM. | KG | 2.450800 | $9.40 | $23.04 |
| ALAMBRON | ALAMBRON | KG | 0.750000 | $18.00 | $13.50 |
| ALAMBRE 16 MM | ALAMBRE GALVANIZADO | KG | 0.030000 | $16.95 | $0.51 |
| Suma de Material | $552.87 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-02 | (1 ALBAÑIL + 1 AYUDANTE DE ALBAÑIL) | JOR | 1.200000 | $576.23 | $691.48 |
| Suma de Mano de Obra | $691.48 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | hora | 0.200000 | $16.88 | $3.38 |
| Suma de Equipo | $3.38 | ||||
| Costo Directo | $1,247.72 |