| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2.2.1.5 | COLUMNA (TIPO C1)SECCION= 40 X 40 CM, CONCRETO HECHO EN OBRA F'C=250 KG/CM2-3/4", CIMBRA 3 CARAS APARENTE, REFORZADO CON 8 VARILLAS DE 3/4" CON. ESTRIBOS DE 3/8" A/C 20 CM GALV. POR IMNERSION EN CALIENTE. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO DE 250 | CONCRETO PREMEZCLADO BOMBEABLE DE 250 KG/CM2, INCLUYE: CONCRETO CPO, REVENIMIENTO 12-14. | M3 | 0.168000 | $949.00 | $159.43 |
| ACERO | ACERO REF.VAR.DIAM. | KG | 25.920000 | $9.40 | $243.65 |
| MADERA-2 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 6.570000 | $5.90 | $38.76 |
| CIMBRAPLAY | CIMBRAPLAY 16 MM | m2 | 0.400000 | $69.00 | $27.60 |
| CLAVO | CLAVO | KG | 0.120000 | $13.50 | $1.62 |
| DIESEL | DIESEL | LT | 0.400000 | $4.20 | $1.68 |
| ALAMBRE 16 MM | ALAMBRE GALVANIZADO | KG | 0.680000 | $16.95 | $11.53 |
| GALVANIZADO POR INME | KG | 26.960000 | $3.00 | $80.88 | |
| BOMBEO | BOMBEO DE CONCRETO | M3 | 0.168000 | $110.00 | $18.48 |
| Suma de Material | $583.63 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-02 | (1 ALBAÑIL + 1 AYUDANTE DE ALBAÑIL) | JOR | 0.100000 | $576.23 | $57.62 |
| Suma de Mano de Obra | $57.62 | ||||
| Herramienta | |||||
| ANDAMIO METALICO | HASTA UNA ALTURA DE 6.00 M | R/DIA | 0.100000 | $45.00 | $4.50 |
| Suma de Herramienta | $4.50 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | hora | 0.033000 | $16.88 | $0.56 |
| Suma de Equipo | $0.56 | ||||
| Costo Directo | $646.31 |