| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| 3.5.10 1 | ZAPATA DE CIMENTACION CORRIDA DE 0.325 M DE BASE Y 0.15 M DE PERALTE, ADOSADA A CONTRATRABE LATERAL DE 0.15 M X 0.20 M DE ALTURA PARA ANCLAJE DE MURO DE SPANCRETE, INCLUYE CIMBRA Y DESCIMBRA COM脷N 0.55 M2 X ML , ACERO FY'=4200 KG/CM2 6 VARS # 3 Y EST. # 2 @ 20 CMS, GALVANIZADO POR INMERSION EN CALIENTE CONCRETO F'C=250KG/CM2-3/4" PREMEZCLADO Y BOMBEADO Y VIBRADO 0.107 M3 X ML | ML |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| GALVANIZADO POR INME | KG | 5.510000 | $3.00 | $16.53 | |
| AGUA | M3 | 0.100000 | $45.00 | $4.50 | |
| Suma de Material | $21.03 | ||||
| Concepto | |||||
| CE-02-01 | CIMBRA COMUN | M2 | 0.730000 | $72.29 | $52.77 |
| CE-03-03 | ACERO DE REFUERZO DEL No. 5 EN CIMENTACION | TON | 0.006000 | $13,029.10 | $78.17 |
| CE-05-02 | F'c= 250 KG/CM2, AGREGADO MAXIMO DE 19 MM., CLASE I | M3 | 0.085000 | $1,181.25 | $100.41 |
| Suma de Concepto | $231.35 | ||||
| Costo Directo | $252.38 |