| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 7:01(E) | ZAPATA DE CIMENTACION CORRIDA (Z-CH1) INCLUYE CIMBRA Y DESCIMBRA COMÚN ANCHO=150 CM PERALTE=30 CM , ACERO FY'=4200 KG/CM2 30.48 KG X ML GALVANIZADO POR INMERSION EN CALIENTE CONCRETO F'C=250KG/CM2-3/4" PREMEZCLADO, BOMBEADO Y VIBRADO | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| GALVANIZADO POR INME | KG | 32.240000 | $3.00 | $96.72 | |
| AGUA | M3 | 0.057000 | $45.00 | $2.57 | |
| Suma de Material | $99.29 | ||||
| Concepto | |||||
| CE-02-01 | CIMBRA COMUN | M2 | 0.600000 | $72.29 | $43.37 |
| CE-03-03 | ACERO DE REFUERZO DEL No. 5 EN CIMENTACION | TON | 0.031000 | $13,029.10 | $403.90 |
| CE-05-02 | F'c= 250 KG/CM2, AGREGADO MAXIMO DE 19 MM., CLASE I | M3 | 0.047000 | $1,181.25 | $55.52 |
| Suma de Concepto | $502.79 | ||||
| Costo Directo | $602.08 |