| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 7:03(D) | REPISON DE REMATE PARA MURO DE SPANCRETE DE .015 X 0.15 CON 4 VARS DE 3/8" Y EST. DE #2 @ 230 CMS CONCRETO F´C=150 KG/CM2 Y CIMBRA APARENTE | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=150 H/O | CONCRETO F'c=150 KG/CM2, HECHO EN OBRA AGREGADO MAXIMO GRAVILLA 3/4" | M3 | 0.023800 | $781.40 | $18.60 |
| GALVANIZADO POR INME | KG | 5.100000 | $3.00 | $15.30 | |
| AGUA | M3 | 0.100000 | $45.00 | $4.50 | |
| Suma de Material | $38.40 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-02 | (1 ALBAÑIL + 1 AYUDANTE DE ALBAÑIL) | JOR | 0.166670 | $576.23 | $96.04 |
| Suma de Mano de Obra | $96.04 | ||||
| Concepto | |||||
| CE-02-01 | CIMBRA COMUN | M2 | 0.400000 | $72.29 | $28.92 |
| CE-03-03 | ACERO DE REFUERZO DEL No. 5 EN CIMENTACION | TON | 0.005000 | $13,029.10 | $65.15 |
| Suma de Concepto | $94.06 | ||||
| Costo Directo | $228.50 |