| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 7:02(C) | TRABE CANALON CENTRAL DE CONCRETO INCLUYE CIMBRA Y DESCIMBRA APARENTE 2.70 M2 X ML SECCION = 30 X 60 CM REFORZADA CON 4 VAR. #8 Y 6 VARS #6 EST.# 3 @ 30 CMS, Y EN CANALON 12 VARS #3 Y EST #3 @ 30 CMS DE ACERO FY'=4200 KG/CM2 GALV. POR INMERSION EN CALIENTE, CONCRETO F'C=250 KG/CM2-3/4" .273 M3 X ML PREMEZCLADO, BOMBEADO Y VIBRADO CON ACELERANTE | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRAPLAY | CIMBRAPLAY 16 MM | m2 | 0.900000 | $69.00 | $62.10 |
| MADERA DE PINO | MADERA PINO 3a. | pt | 4.900000 | $5.90 | $28.91 |
| CLAVO | CLAVO | KG | 0.000000 | $13.50 | $0.00 |
| DIESEL | DIESEL | LT | 0.500000 | $4.20 | $2.10 |
| GALVANIZADO POR INME | KG | 57.200000 | $3.00 | $171.60 | |
| AGUA | M3 | 0.200000 | $45.00 | $9.00 | |
| Suma de Material | $273.71 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-04 | (1 OFICIAL CARPINTERO OBRA NEGRA + 1 AYUDANTE) | jor | 0.140000 | $576.23 | $80.67 |
| Suma de Mano de Obra | $80.67 | ||||
| Concepto | |||||
| CE-03-03 | ACERO DE REFUERZO DEL No. 5 EN CIMENTACION | TON | 0.055000 | $13,029.10 | $716.60 |
| CE-05-02 | F'c= 250 KG/CM2, AGREGADO MAXIMO DE 19 MM., CLASE I | M3 | 0.273000 | $1,181.25 | $322.48 |
| Suma de Concepto | $1,039.08 | ||||
| Costo Directo | $1,393.46 |