| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2.2.2. 5 | NERVADURA EN ESTRUCTURA (N5) INCLUYE CIMBRA Y DESCIMBRA SECCION = 15 X35 CM REFORZADA CON 4 VAR. #3, Y EST. # 2 @ 20 CMS DE ACERO FY'=4200 KG/CM2 CONCRETO PREMEZCLADO F'C=250 KG/CM2-3/4" BOMBEADO, VIBRADO Y CON ACELERANTE GALVANIZADO POR INMERSION EN CALIENTE | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO DE 250 | CONCRETO PREMEZCLADO BOMBEABLE DE 250 KG/CM2, INCLUYE: CONCRETO CPO, REVENIMIENTO 12-14. | M3 | 0.054000 | $949.00 | $51.25 |
| BOMBEO | BOMBEO DE CONCRETO | M3 | 0.054000 | $110.00 | $5.94 |
| ACERO | ACERO REF.VAR.DIAM. | KG | 4.460000 | $9.40 | $41.92 |
| ALAMBRE 16 MM | ALAMBRE GALVANIZADO | KG | 0.167000 | $16.95 | $2.83 |
| GALVANIZADO POR INME | KG | 4.638000 | $3.00 | $13.91 | |
| Suma de Material | $115.85 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-02 | (1 ALBAÑIL + 1 AYUDANTE DE ALBAÑIL) | JOR | 0.055560 | $576.23 | $32.02 |
| Suma de Mano de Obra | $32.02 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | hora | 0.070000 | $16.88 | $1.18 |
| Suma de Equipo | $1.18 | ||||
| Costo Directo | $149.05 |