| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 7:02(D) | TRABE CANALON LINDERO DE CONCRETO INCLUYE CIMBRA Y DESCIMBRA APARENTE 2.45 M2 X ML SECCION = 30 X 60 CM REFORZADA CON 12 VAR #8 Y 6 VARS #6 EST.# 3 @ 30 CMS, Y EN CANALON 12 VARS #5 Y EST #2 @ 20 CMS DE ACERO FY'=4200 KG/CM2 GALV. POR INMERSION EN CALIENTE, CONCRETO F'C=250 KG/CM2-3/4" .252 M3 X ML PREMEZCLADO, BOMBEADO Y VIBRADO CON ACELERANTE | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMBRAPLAY | CIMBRAPLAY 16 MM | m2 | 0.610000 | $69.00 | $42.09 |
| MADERA DE PINO | MADERA PINO 3a. | pt | 3.900000 | $5.90 | $23.01 |
| CLAVO | CLAVO | KG | 0.300000 | $13.50 | $4.05 |
| DIESEL | DIESEL | LT | 0.500000 | $4.20 | $2.10 |
| GALVANIZADO POR INME | KG | 104.000000 | $3.00 | $312.00 | |
| AGUA | M3 | 0.200000 | $45.00 | $9.00 | |
| Suma de Material | $392.25 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-04 | (1 OFICIAL CARPINTERO OBRA NEGRA + 1 AYUDANTE) | jor | 0.120000 | $576.23 | $69.15 |
| Suma de Mano de Obra | $69.15 | ||||
| Concepto | |||||
| CE-03-03 | ACERO DE REFUERZO DEL No. 5 EN CIMENTACION | TON | 0.100000 | $13,029.10 | $1,302.91 |
| CE-05-02 | F'c= 250 KG/CM2, AGREGADO MAXIMO DE 19 MM., CLASE I | M3 | 0.252000 | $1,181.25 | $297.68 |
| Suma de Concepto | $1,600.59 | ||||
| Costo Directo | $2,061.98 |