| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 5:06(A) | FIRME DE 5 CMS DE ESP. DE CONCRETO MEZCLADO CON FIBERMESH EN FONDO DE CISTERNA | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=150 H/O | CONCRETO F'c=150 KG/CM2, HECHO EN OBRA AGREGADO MAXIMO GRAVILLA 3/4" | M3 | 0.051500 | $781.40 | $40.24 |
| MADERA PINO BARROTE | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 1.390000 | $5.90 | $8.20 |
| CLAVO | CLAVO | KG | 0.115000 | $13.50 | $1.55 |
| Suma de Material | $50.00 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-02 | (1 ALBAÑIL + 1 AYUDANTE DE ALBAÑIL) | JOR | 0.055560 | $576.23 | $32.02 |
| Suma de Mano de Obra | $32.02 | ||||
| Costo Directo | $82.01 |