| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2.2.1.9 | NERVADURA EN ESTRUCTURA (N3) SECCION = 20 X25 CM REFORZADA CON 5 VAR. #3 Y EST. # 2 @ 20 CMS, DE ACERO FY'=4200 KG/CM2 GALV. EN CALIENTE , CONCRETO PREMEZCLADO F'C=250 KG/CM2-3/4" BOMBEADO Y VIBRADO CON ACELERANTE | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO DE 250 | CONCRETO PREMEZCLADO BOMBEABLE DE 250 KG/CM2, INCLUYE: CONCRETO CPO, REVENIMIENTO 12-14. | M3 | 0.053000 | $949.00 | $50.30 |
| BOMBEO | BOMBEO DE CONCRETO | M3 | 0.053000 | $110.00 | $5.83 |
| ACERO | ACERO REF.VAR.DIAM. | KG | 4.890000 | $9.40 | $45.97 |
| ALAMBRE 16 MM | ALAMBRE GALVANIZADO | KG | 0.100000 | $16.95 | $1.70 |
| GALVANIZADO POR INME | KG | 2.615000 | $3.00 | $7.85 | |
| Suma de Material | $111.63 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-02 | (1 ALBAÑIL + 1 AYUDANTE DE ALBAÑIL) | JOR | 0.070000 | $576.23 | $40.34 |
| Suma de Mano de Obra | $40.34 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | hora | 0.023000 | $16.88 | $0.39 |
| Suma de Equipo | $0.39 | ||||
| Costo Directo | $152.36 |