| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| 2.2.1 11 | CASTILLO DE CONCRETO (K15)SECCION= 20 X 105 CM, CONCRETO F'C=150 KG/CM2-3/4", CIMBRA 3 CARAS, REFORZADO CON 10 VAR. DE 1/2" Y EST # 2 @ 15 CMS GALVANIZADO POR INMERSION EN CALIENTE | ML |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=150 H/O | CONCRETO F'c=150 KG/CM2, HECHO EN OBRA AGREGADO MAXIMO GRAVILLA 3/4" | M3 | 0.216000 | $781.40 | $168.78 |
| ACERO | ACERO REF.VAR.DIAM. | KG | 20.590000 | $9.40 | $193.55 |
| MADERA-2 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 6.590000 | $5.90 | $38.88 |
| CIMBRAPLAY | CIMBRAPLAY 16 MM | m2 | 0.440000 | $69.00 | $30.36 |
| CLAVO | CLAVO | KG | 0.350000 | $13.50 | $4.73 |
| DIESEL | DIESEL | LT | 0.400000 | $4.20 | $1.68 |
| ALAMBRE 16 MM | ALAMBRE GALVANIZADO | KG | 0.560000 | $16.95 | $9.49 |
| GALVANIZADO POR INME | KG | 21.410000 | $3.00 | $64.23 | |
| Suma de Material | $511.70 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-02 | (1 ALBA脩IL + 1 AYUDANTE DE ALBA脩IL) | JOR | 0.180000 | $576.23 | $103.72 |
| Suma de Mano de Obra | $103.72 | ||||
| Herramienta | |||||
| ANDAMIO METALICO | HASTA UNA ALTURA DE 6.00 M | R/DIA | 0.100000 | $45.00 | $4.50 |
| Suma de Herramienta | $4.50 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | hora | 0.033000 | $16.88 | $0.56 |
| Suma de Equipo | $0.56 | ||||
| Costo Directo | $620.47 |