| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 7:01(G) | CONTRATRABE DE CIMENTACION (T-CH1) INCLUYE CIMBRA Y DESCIMBRA COMÚN SECCION 0.70 X 0.50 M REFORZADO CON 8 VARILLAS DE #6 Y 6 VARS DEL # 5 ESTRIBOS DEL No 3 @ 20 CMS GALVANIZADO POR INMERSION EN CALIENTE, CONCRETO F'C=250 KG/CM2-3/4". PREMEZCLADO BOMBEADO Y VIBRADO | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| GALVANIZADO POR INME | KG | 41.600000 | $3.00 | $124.80 | |
| AGUA | M3 | 0.125000 | $45.00 | $5.63 | |
| BOMBEO | BOMBEO DE CONCRETO | M3 | 0.360000 | $110.00 | $39.60 |
| Suma de Material | $170.03 | ||||
| Concepto | |||||
| CE-02-01 | CIMBRA COMUN | M2 | 1.400000 | $72.29 | $101.21 |
| CE-03-03 | ACERO DE REFUERZO DEL No. 5 EN CIMENTACION | TON | 0.040000 | $13,029.10 | $521.16 |
| CE-05-02 | F'c= 250 KG/CM2, AGREGADO MAXIMO DE 19 MM., CLASE I | M3 | 0.360500 | $1,181.25 | $425.84 |
| Suma de Concepto | $1,048.21 | ||||
| Costo Directo | $1,218.24 |