| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2.2.1 2 | CASTILLO DE CONCRETO (K2)SECCION= 15 X 25 CM, CONCRETO F'C=150 KG/CM2-3/4", CIMBRA 2 CARAS, REFORZADO CON 4 VAR. DE 1/2" Y EST. DEL # 2 @ 15 CM. GALVANIZADO POR INMERSION EN CALIENTE | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=150 H/O | CONCRETO F'c=150 KG/CM2, HECHO EN OBRA AGREGADO MAXIMO GRAVILLA 3/4" | M3 | 0.038000 | $781.40 | $29.69 |
| ACERO | ACERO REF.VAR.DIAM. | KG | 5.640000 | $9.40 | $53.02 |
| MADERA-2 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 3.280000 | $5.90 | $19.35 |
| DIESEL | DIESEL | LT | 0.258500 | $4.20 | $1.09 |
| ALAMBRE 16 MM | ALAMBRE GALVANIZADO | KG | 0.220000 | $16.95 | $3.73 |
| CLAVO | CLAVO | KG | 0.200000 | $13.50 | $2.70 |
| GALVANIZADO POR INME | KG | 5.860000 | $3.00 | $17.58 | |
| Suma de Material | $127.16 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-02 | (1 ALBAÑIL + 1 AYUDANTE DE ALBAÑIL) | JOR | 0.076920 | $576.23 | $44.32 |
| Suma de Mano de Obra | $44.32 | ||||
| Herramienta | |||||
| ANDAMIO METALICO | HASTA UNA ALTURA DE 6.00 M | R/DIA | 0.100000 | $45.00 | $4.50 |
| Suma de Herramienta | $4.50 | ||||
| Costo Directo | $175.98 |