| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2.2.1.15 | NERVADURA EN ESTRUCTURA (N4) SECCION = 40 X25 CM REFORZADA CON 8 VAR. #5 Y 4 BASTONES DEL No. 5 X 4.50 CMS. Y EST. # 3 @ 20 CMS. DE ACERO FY'=4200 KG/CM2 GALV. POR INMERSION EN CALIENTE CONCRETO PREMEZCLADO F'C=250 KG/CM2-3/4" BOMBEADO Y VIBRADO, CON ACELERANTE | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO DE 250 | CONCRETO PREMEZCLADO BOMBEABLE DE 250 KG/CM2, INCLUYE: CONCRETO CPO, REVENIMIENTO 12-14. | M3 | 0.100000 | $949.00 | $94.90 |
| BOMBEO | BOMBEO DE CONCRETO | M3 | 0.100000 | $110.00 | $11.00 |
| ACELERANTE | ACELERANTE PARA CONCRETO | LT | 0.500000 | $30.00 | $15.00 |
| ACERO | ACERO REF.VAR.DIAM. | KG | 3.900000 | $9.40 | $36.66 |
| ALAMBRE 16 MM | ALAMBRE GALVANIZADO | KG | 0.300000 | $16.95 | $5.09 |
| GALVANIZADO POR INME | KG | 4.050000 | $3.00 | $12.15 | |
| Suma de Material | $174.80 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-02 | (1 ALBAÑIL + 1 AYUDANTE DE ALBAÑIL) | JOR | 0.083330 | $576.23 | $48.02 |
| Suma de Mano de Obra | $48.02 | ||||
| Equipo | |||||
| VIBRADOR CONCRETO | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES | hora | 0.070000 | $16.88 | $1.18 |
| Suma de Equipo | $1.18 | ||||
| Costo Directo | $223.99 |