| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2.2.1 5 | CASTILLO DE CONCRETO (K6)SECCION= 15 X 35 CM, CONCRETO F'C=150 KG/CM2-3/4", CIMBRA 2 CARAS, REFORZADO CON 6 VAR. DE 1/2# Y EST. # 2 @ 15 CMS, GALVANIZADO POR INMERSION EN CALIENTE | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO F-C=150 H/O | CONCRETO F'c=150 KG/CM2, HECHO EN OBRA AGREGADO MAXIMO GRAVILLA 3/4" | M3 | 0.054000 | $781.40 | $42.20 |
| ACERO | ACERO REF.VAR.DIAM. | KG | 8.040000 | $9.40 | $75.58 |
| MADERA-2 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 3.280000 | $5.90 | $19.35 |
| CIMBRAPLAY | CIMBRAPLAY 16 MM | m2 | 0.200000 | $69.00 | $13.80 |
| DIESEL | DIESEL | LT | 0.258500 | $4.20 | $1.09 |
| ALAMBRE 16 MM | ALAMBRE GALVANIZADO | KG | 0.250000 | $16.95 | $4.24 |
| CLAVO | CLAVO | KG | 0.220000 | $13.50 | $2.97 |
| GALVANIZADO POR INME | KG | 8.360000 | $3.00 | $25.08 | |
| Suma de Material | $184.30 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-02 | (1 ALBAÑIL + 1 AYUDANTE DE ALBAÑIL) | JOR | 0.125000 | $576.23 | $72.03 |
| Suma de Mano de Obra | $72.03 | ||||
| Herramienta | |||||
| ANDAMIO METALICO | HASTA UNA ALTURA DE 6.00 M | R/DIA | 0.100000 | $45.00 | $4.50 |
| Suma de Herramienta | $4.50 | ||||
| Costo Directo | $260.83 |