| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 040238 | DALA D-1 DE LIGA, INCLUYE CIMBRA Y DESCIMBRA SECCION= 15 X 20 CM, CONCRETO F'C=150 KG/CM2-3/4", REFORZADA CON ARMEX DE 15 X 15 - 4 | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 1.106000 | $14.77 | $16.34 |
| 1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 1.106000 | $14.77 | $16.34 |
| 0110-00 | ARMADURA SOLDADA PARA CASTILLO ARMEX 15 X 15 - 4 | PZA | 0.170000 | $62.61 | $10.64 |
| 0110-00 | ARMADURA SOLDADA PARA CASTILLO ARMEX 15 X 15 - 4 | PZA | 0.170000 | $62.61 | $10.64 |
| 0082-00 | ALAMBRE RECOCIDO NO. 16 | KG | 0.200000 | $11.00 | $2.20 |
| 0082-00 | ALAMBRE RECOCIDO NO. 16 | KG | 0.200000 | $11.00 | $2.20 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.125000 | $12.50 | $1.56 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.125000 | $12.50 | $1.56 |
| 0950-05 | DIESEL | LT | 0.400000 | $5.00 | $2.00 |
| 0950-05 | DIESEL | LT | 0.400000 | $5.00 | $2.00 |
| Suma de Material | $65.48 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.083333 | $783.11 | $65.26 |
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.083333 | $783.11 | $65.26 |
| Suma de Mano de Obra | $130.52 | ||||
| Auxiliar | |||||
| 03-2170 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 1 1/2" | M3 | 0.031500 | $801.10 | $25.23 |
| 03-2170 | CONCRETO HECHO EN OBRA F'C=150 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 1 1/2" | M3 | 0.031500 | $801.10 | $25.23 |
| 03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3¬ USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.090900 | $20.07 | $1.82 |
| 03-7012 | ANDAMIO DE CABALLETES Y TABLONES CONSTRUIDO CON MADERA DE PINO DE 3¬ USADO PARA ALTURAS DE 1.50 A 3.00 M. | USO | 0.090900 | $20.07 | $1.82 |
| Suma de Auxiliar | $54.12 | ||||
| Costo Directo | $250.12 |