| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 030406 | LOSA PLANA EN ESTRUCTURA, PERALTE = 12 CM CIMBRA APARENTE REFORZADA CON 72 KG DE ACERO POR M3, CONCRETO F'C = 200 - 3/4" | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| 03-2060 | CONCRETO HECHO EN OBRA F'C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.120000 | $797.23 | $95.67 |
| 03-2060 | CONCRETO HECHO EN OBRA F'C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.120000 | $797.23 | $95.67 |
| Suma de Auxiliar | $191.34 | ||||
| Concepto | |||||
| 020226 | CIMBRA APARENTE EN LOSA | M2 | 1.000000 | $116.58 | $116.58 |
| 020226 | CIMBRA APARENTE EN LOSA | M2 | 1.000000 | $116.58 | $116.58 |
| 020225 | CIMBRA COMUN EN LOSA DE 12 CMS DE ALTURA FRONTERA | M2 | 0.250000 | $133.86 | $33.47 |
| 020225 | CIMBRA COMUN EN LOSA DE 12 CMS DE ALTURA FRONTERA | M2 | 0.250000 | $133.86 | $33.47 |
| 020319 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 3 DIAMETRO 3/8" | TON | 0.015000 | $13,400.84 | $201.01 |
| 020319 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 3 DIAMETRO 3/8" | TON | 0.015000 | $13,400.84 | $201.01 |
| Suma de Concepto | $702.12 | ||||
| Costo Directo | $893.45 |