| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALB.01 | FIRME DE CONCRETO DE 10 CM. DE ESPESOR, F´c=150 KG/CM2 ARMADO CON MALLA 6X6/10-10. INCLUYE: MATERIALES, MANO DE OBRA, HERRAMIENTA Y EQUIPO. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MACMPL4X4X81/4 | Polin de 4" x 4" regular | pt | 0.525021 | $6.25 | $3.28 |
| A1BAR0N3/8 | Varilla de acero corrugada No.3 (3/8"Ø), Fy=4200 kg/cm2. | kg | 0.025498 | $7.30 | $0.19 |
| SEPAROL | Separol, desmoldante para cimbras | Lt | 0.016000 | $16.96 | $0.27 |
| A1FAR010 | Malla electrosoldada 6x6/10-10 | m2 | 1.050000 | $10.87 | $11.41 |
| A4BAR013 | Alambre recocido Calibre 16 | kg | 0.038222 | $12.61 | $0.48 |
| ANTISOL | Antisol membrana de curado SIKA | Lt | 0.125000 | $11.22 | $1.40 |
| Suma de Material | $17.04 | ||||
| Mano de Obra | |||||
| JOGP014 | Cuadrilla de 1 albañil + 1 ayudante + cabo | Jor | 0.076923 | $481.29 | $37.02 |
| Suma de Mano de Obra | $37.02 | ||||
| Herramienta | |||||
| 2HER | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| EQ-VIB | Vibrador de Concreto mot. gasolina 3 hp Kolher | Hora | 0.000000 | $40.91 | $0.00 |
| Suma de Equipo | $0.00 | ||||
| Auxiliar | |||||
| FCO0003 | Concreto f'c=150kg/cm2, resistencia normal, agreg. max. 20mm., fabricado en obra con revolvedora; incluye: acarreos a 1a. estacion a 20.00m. | m3 | 0.105000 | $800.98 | $84.10 |
| Suma de Auxiliar | $84.10 | ||||
| Costo Directo | $138.16 |