| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 030402 | LOSA PLANA EN RAMPA PARA ESCALERA, PERALTE = 10 CM CIMBRA APARENTE REFORZADA CON 60 KG DE ACERO POR M3, CONCRETO F'C = 200 - 3/4" INCL. CIMBRA Y DECIMBRA, MATERIALES Y HERRAMIENTA. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| 03-2060 | CONCRETO HECHO EN OBRA F'C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.100000 | $797.23 | $79.72 |
| Suma de Auxiliar | $79.72 | ||||
| Concepto | |||||
| 020226 | CIMBRA APARENTE EN LOSA | M2 | 1.000000 | $116.58 | $116.58 |
| 020319 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 3 DIAMETRO 3/8" | TON | 0.006000 | $13,400.84 | $80.41 |
| Suma de Concepto | $196.99 | ||||
| Costo Directo | $276.71 |