| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| ALB.10 | TRABE T-1 DE 20 X 50 CM. HECHA DE CONCRETO F'c = 200 KGS / CM2. ARMADA CON 4 VS. 3/8" Y 4 VS. 1/2", Fy= 4,200 KGS/ CM2, ESTRIBOS DE 1/4" @ 15 CMS Fy= 4200 KGS / CM2. INCLUYE: MATERIALES, MANO DE OBRA, HERRAMIENTA Y EQUIPO | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| A1BAR0N3/8 | Varilla de acero corrugada No.3 (3/8"Ø), Fy=4200 kg/cm2. | kg | 2.455200 | $7.30 | $17.92 |
| A1BAR0N1/2 | Varilla de acero corrugada No.4 (1/2"Ø), Fy=4200 kg/cm2. | kg | 4.382400 | $7.30 | $31.99 |
| A1AAR005 | Alambrón varilla No. 2 1/4" | kg | 3.207600 | $9.00 | $28.87 |
| A4BAR013 | Alambre recocido Calibre 16 | kg | 0.200000 | $12.61 | $2.52 |
| ANTISOL | Antisol membrana de curado SIKA | Lt | 0.105000 | $11.22 | $1.18 |
| Suma de Material | $82.48 | ||||
| Mano de Obra | |||||
| JOGP014 | Cuadrilla de 1 albañil + 1 ayudante + cabo | Jor | 0.285714 | $481.29 | $137.51 |
| Suma de Mano de Obra | $137.51 | ||||
| Herramienta | |||||
| 2HER | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| EQ-VIB | Vibrador de Concreto mot. gasolina 3 hp Kolher | Hora | 0.105000 | $40.91 | $4.30 |
| Suma de Equipo | $4.30 | ||||
| Auxiliar | |||||
| CIMCYCDC | Madera para cimbra Común en castillos, cadenas y registros, a base de triplay de 16 mm y barrotes de 2"x4". Incluye: Madera, clavos, alambre y desmoldante | m2 | 1.200000 | $25.97 | $31.16 |
| FCO0005 | Concreto f'c=200kg/cm2, resistencia normal, agregado maximo 20mm., fabricado en obra con revolvedora; incluye: acarreos a 1a. estacion a 20.00m. | m3 | 0.105000 | $863.25 | $90.64 |
| AND004 | Andamio de 4.00 m. de altura, construido con una torre de trabajo de tubo de acero, con ruedas y base de tablones de madera. | r/d | 0.625000 | $44.17 | $27.61 |
| Suma de Auxiliar | $149.41 | ||||
| Costo Directo | $373.70 |