| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 030308 | TRABE EN CIMENTACION INCLUYE CIMBRA Y DESCIMBRA SECCION = 15 X 30 CM CIMBRA COMUN REFORZADA CON 130 KG/M3 DE ACERO FY'=4200 KG/CM2 CONCRETO F'C=150 KG/CM2- AGRAGADO MAXIMO 3/4" | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CPAPR015 | Concreto premez. f'c=200 kg/cm2 RN,tma= 20mm, rev 10 clase 2 grd A no bombeable, marca Lacosa | m3 | 0.045000 | $845.00 | $38.03 |
| Suma de Material | $38.03 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.055556 | $783.11 | $43.51 |
| Suma de Mano de Obra | $43.51 | ||||
| Concepto | |||||
| 020222 | CIMBRA APARENTE EN TRABES DE 25 X 40 CM. | M2 | 0.600000 | $203.03 | $121.82 |
| 020323 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 5 DIAMETRO 5/8" | TON | 0.011000 | $4,586.81 | $50.45 |
| Suma de Concepto | $172.27 | ||||
| Costo Directo | $253.80 |