| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| 10102A01 | Protecci贸n de Concreto Armado para Acometida Aereo-Subterranea de: 0.20 x 0.90 x 3.10m (Segun Plano) | Pieza |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO-01 | ACERO DEL # 3 ( 1/2") AL # 6 (3/4) | KG* | 22.000000 | $5.45 | $119.90 |
| ACERO-02 | ALAMBRE RECOCIDO GALVANIZADO | KG | 0.660000 | $25.47 | $16.81 |
| CIMBRA-01 | CIMBRAPLAY | M2 | 1.330000 | $73.76 | $98.10 |
| CIMBRA-02 | CLAVO | Kg. | 1.500000 | $8.77 | $13.16 |
| CIMBRA-04 | MADERA DE PINO | PT | 4.000000 | $5.15 | $20.60 |
| COMBUSTIBLE 01 | DIESEL | LT | 2.000000 | $4.80 | $9.60 |
| CONCRETO PRE-05 | CONCRETO PREMEZCLADO DE F'C= 250 KG/CM2 | M3 | 0.600000 | $720.00 | $432.00 |
| Suma de Material | $710.17 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 01 | (1 pe贸n). | JOR | 0.300000 | $206.11 | $61.83 |
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Pe贸n) | JOR | 1.500000 | $477.52 | $716.28 |
| Suma de Mano de Obra | $778.11 | ||||
| Equipo | |||||
| MAQUINARIA-23 | VIBRADOR PARA CONCRETO KOHLER 8 HP BASE TIPO JAULA | HR** | 0.911144 | $13.03 | $11.87 |
| Suma de Equipo | $11.87 | ||||
| Costo Directo | $1,500.15 |