| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 11 | CONCRETO HIDRAULICO P.U.O.T. SIMPLE COLADO EN SECO DE F`C=150 KG./CM2 | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| PEON | PEON | JOR | 1.000000 | $165.66 | $165.66 |
| OFALBAÑIL | OFICIAL ALBAÑIL | JOR | 0.333333 | $302.53 | $100.84 |
| Suma de Mano de Obra | $266.50 | ||||
| Herramienta | |||||
| HER | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| EQ 17 VIBRAD CONCR | VIBRADOR PARA CONCRETO | Hora | 1.000000 | $42.60 | $42.60 |
| Suma de Equipo | $42.60 | ||||
| Auxiliar | |||||
| CONC F-C=150 | CONCRETO F'C=150 KG/CM2 | m3 | 1.050000 | $533.28 | $559.94 |
| CIMBRA | CIMBRA | m2 | 5.500000 | $108.03 | $594.17 |
| ELAB CONC OBRA | ELABORACION DE CONCRETO EN OBRA | m3 | 1.050000 | $134.43 | $141.15 |
| Suma de Auxiliar | $1,295.26 | ||||
| Costo Directo | $1,604.36 |