| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 17 | CARPETAS ASFALTICAS CON MEZCLA EN CALIENTE a) CARPETAS DE CONCRETO ASFALTICO P.U.O.T. 1) COMPACATADAS AL CIEN POR CIENTO (100%) | M3. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CARP-ASFAL | CARPETA ASFALTICA DE PLANTA | M3 | 1.350000 | $800.00 | $1,080.00 |
| EMUL-ASFAL | EMULSION ASFALTICA PARA RIEGO DE LIGA | LT | 0.500000 | $6.00 | $3.00 |
| Suma de Material | $1,083.00 | ||||
| Mano de Obra | |||||
| AYUD RASTRILLERO | AYUDANTE RASTRILLERO | jor | 0.055556 | $181.31 | $10.07 |
| AYUD POREADOR | AYUDANTE POREADOR | jor | 0.055556 | $181.31 | $10.07 |
| Suma de Mano de Obra | $20.15 | ||||
| Herramienta | |||||
| HER | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| EQ 12 PETROLIZADORA | PETROLIZADORA SEAMAN GUNNISON DE 10000 LTS. DE 155 HP. MOTOR VAM. MOD. 6558 BOMBA 756 LPM BARRA 3.66 M. | hora | 0.005000 | $282.82 | $1.41 |
| EQ 11 PAVIMENT | PAVIMENTADORA ASFALTICA JHON DEERE DIESEL . | hora | 0.020833 | $536.17 | $11.17 |
| EQ 10 RODVIBRA | COMPACTADOR VIBRATORIO VAG 55 | hora | 0.020833 | $306.25 | $6.38 |
| Suma de Equipo | $18.96 | ||||
| Auxiliar | |||||
| ACA 1ER CAM PRO PAV | ACARREO 1er KM PAVIMENTO UTILIZANDO CAMIONES PROPIOS | m3 | 0.500000 | $2.98 | $1.49 |
| ACA 1ER KM SIND PAV | ACARREO 1er KM PAVIMENTO UTILIZANDO CAMIONES DEL SINDICATO | m3 | 0.500000 | $6.07 | $3.04 |
| ACA 2-20 CAM PRO PAV | ACARREO DEL KM 2 AL 20 UTILIZANDO CAMIONES PROPIOS | m3 | 10.000000 | $2.32 | $23.20 |
| ACA 2-20 SIND PAV | ACARREO DEL KM 2 AL 20 PAVIMENTO CAMIONES DEL SINDICATO | m3 | 10.000000 | $2.71 | $27.10 |
| ACA 21 AD CAM PRO PA | ACARREO DEL KM 21 EN ADELANTE EN PAVIMENTO EN CAMIONES PROPIOS | m3 | 30.000000 | $2.09 | $62.70 |
| ACA 21 AD SND PAV | ACARREO DEL KM 21 EN ADELANTE EN PAVIMENTO CON CAMIONES DEL SINDICATO | m3 | 30.000000 | $2.56 | $76.80 |
| ACARR 2-20 PRO TE | ACARREO DEL KM 2 AL 20 EN TERRACERIAS CON CAMIONES PROPIOS | m3 | 2.000000 | $2.32 | $4.64 |
| ACARR 2-20 SIND TE | ACARREO DEL KM 2-20 EN TERRACERIACON CAMIONES DEL SINDICATO | m3 | 2.000000 | $3.41 | $6.82 |
| Suma de Auxiliar | $205.79 | ||||
| Costo Directo | $1,327.89 |