| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| E.P.6 | FABRICACION DE POZO DE VISTA TIPO COMUN HASTA 1.50M DE PROFUNDIDAD | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PIEDRAB | PIEDRA BRAZA | M3 | 0.689000 | $100.00 | $68.90 |
| CEMENTOG | CEMENTO GRIS | TON | 0.008700 | $1,565.00 | $13.62 |
| MAAC0002 | ACERO REFUERZO F'Y= 4200 KG/CM2 | TON | 0.002800 | $10,500.00 | $29.40 |
| MACO0001 | AGUA | M3 | 1.650000 | $35.00 | $57.75 |
| MAT00163 | TABIQUE ROJO RECOCIDO | PZA | 863.000000 | $1.80 | $1,553.40 |
| BROCFOFO | BROCAL Y TAPA FO.F.O. | PZA | 1.000000 | $820.00 | $820.00 |
| Suma de Material | $2,543.07 | ||||
| Mano de Obra | |||||
| 1A5P | CUADRILLA No 22 (1 ALBAÑIL + 5 PEONES) | jor | 1.000000 | $1,244.69 | $1,244.69 |
| Suma de Mano de Obra | $1,244.69 | ||||
| Auxiliar | |||||
| BASICO27 | CONCRETO F'c= 150kg/cm2 HECHO EN OBRA | M3 | 0.176000 | $618.40 | $108.84 |
| BASICO46 | MORTERO CEMENTO ARENA 1:3 | M3 | 0.350000 | $716.78 | $250.87 |
| Suma de Auxiliar | $359.71 | ||||
| Costo Directo | $4,147.47 |