| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| E.P.6C | FABRICACION DE POZO DE VISTA TIPA COMUN DE 2.75M A 3.00M DE PROFUNDIDAD | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PIEDRAB | PIEDRA BRAZA | M3 | 0.689000 | $100.00 | $68.90 |
| MACO0001 | AGUA | M3 | 3.603463 | $35.00 | $126.12 |
| MAT00163 | TABIQUE ROJO RECOCIDO | PZA | 1,930.000000 | $1.80 | $3,474.00 |
| CEMENTOG | CEMENTO GRIS | TON | 0.018918 | $1,565.00 | $29.61 |
| BROCFOFO | BROCAL Y TAPA FO.F.O. | PZA | 1.000000 | $820.00 | $820.00 |
| MAAC0002 | ACERO REFUERZO F'Y= 4200 KG/CM2 | TON | 0.004943 | $10,500.00 | $51.90 |
| Suma de Material | $4,570.53 | ||||
| Mano de Obra | |||||
| 1A5P | CUADRILLA No 22 (1 ALBAÑIL + 5 PEONES) | jor | 1.000000 | $1,244.69 | $1,244.69 |
| Suma de Mano de Obra | $1,244.69 | ||||
| Auxiliar | |||||
| BASICO27 | CONCRETO F'c= 150kg/cm2 HECHO EN OBRA | M3 | 0.176000 | $618.40 | $108.84 |
| BASICO46 | MORTERO CEMENTO ARENA 1:3 | M3 | 0.650000 | $716.78 | $465.91 |
| Suma de Auxiliar | $574.75 | ||||
| Costo Directo | $6,389.96 |