| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| N·CTR·CAR·1·02·003-1 | De f'c =250 kg/cm² en columnas | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC PREMEZ 250 | CONCRETO PREMEZCLADO 250 KG/CM2 | m3 | 1.030000 | $1,100.25 | $1,133.26 |
| 0171-95 | CURACONSA BLANCO, MENBRANA DE CURADO PARA CONCRETO | lt | 0.200000 | $16.00 | $3.20 |
| Suma de Material | $1,136.46 | ||||
| Mano de Obra | |||||
| 02-0440 | CUADRILLA No 44 ( 1 ALBAÑIL + 4 PEONES ) | JOR | 0.200000 | $1,554.18 | $310.84 |
| Suma de Mano de Obra | $310.84 | ||||
| Equipo | |||||
| 03-4020 | VIBRADOR PARA CONCRETO DYNAPAC-KOHLER K-91 4 H.P. LONGITUD 14 PIES INCLUYE OPERACION | Hora | 0.500000 | $59.32 | $29.66 |
| Suma de Equipo | $29.66 | ||||
| Auxiliar | |||||
| CIMBRA COLUMNAS | CIMBRA EN COLUMNAS | m2 | 5.000000 | $149.89 | $749.45 |
| Suma de Auxiliar | $749.45 | ||||
| Costo Directo | $2,226.40 |