| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| E.P.6A | FABRICACION DE POZO DE VISTA TIPO COMUN DE 1.5M A 1.75M DE PROFUNDIDAD | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MAAC0002 | ACERO REFUERZO F'Y= 4200 KG/CM2 | TON | 0.003000 | $10,500.00 | $31.50 |
| MACO0001 | AGUA | M3 | 1.130000 | $35.00 | $39.55 |
| CEMENTOG | CEMENTO GRIS | TON | 0.010390 | $1,565.00 | $16.26 |
| PIEDRAB | PIEDRA BRAZA | M3 | 0.689000 | $100.00 | $68.90 |
| MAT00163 | TABIQUE ROJO RECOCIDO | PZA | 1,039.000000 | $1.80 | $1,870.20 |
| BROCFOFO | BROCAL Y TAPA FO.F.O. | PZA | 1.000000 | $820.00 | $820.00 |
| Suma de Material | $2,846.41 | ||||
| Mano de Obra | |||||
| 1A5P | CUADRILLA No 22 (1 ALBAÑIL + 5 PEONES) | jor | 1.000000 | $1,244.69 | $1,244.69 |
| Suma de Mano de Obra | $1,244.69 | ||||
| Auxiliar | |||||
| BASICO46 | MORTERO CEMENTO ARENA 1:3 | M3 | 0.400000 | $716.78 | $286.71 |
| BASICO27 | CONCRETO F'c= 150kg/cm2 HECHO EN OBRA | M3 | 0.176000 | $618.40 | $108.84 |
| Suma de Auxiliar | $395.55 | ||||
| Costo Directo | $4,486.65 |