| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CAR-1-04-006/0 | CARPETA DE CONCRETO ASFALTICO, P.U.O.T. | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ELABMEZ | CARPETA ASFALTICA | M3 | 1.260000 | $950.00 | $1,197.00 |
| Suma de Material | $1,197.00 | ||||
| Mano de Obra | |||||
| 5P | CUADRILLA No 27 (5 PEONES + 1 CABO) | JOR | 0.100000 | $1,136.71 | $113.67 |
| Suma de Mano de Obra | $113.67 | ||||
| Equipo | |||||
| EQDIE003 | CAMION PIPA DE AGUA 8,000 LTS | hora | 0.050000 | $323.25 | $16.16 |
| EQMION | CAMION DE VOLTEO DE 7 M3 | hora | 0.050000 | $274.05 | $13.70 |
| EQBARR01 | BARREDORA FRONTAL | hora | 0.050000 | $114.52 | $5.73 |
| EQTANDEN | COMPACTADOR CATERPILLAR DOBLE RODILLO | hora | 0.125000 | $434.51 | $54.31 |
| EQCOMNEU | COMPACTADOR NEUMATICOS DUO-PACTOR | hora | 0.125000 | $429.78 | $53.72 |
| EQPAVI | EXTENDEDORA FINISHER | hora | 0.150000 | $566.41 | $84.96 |
| Suma de Equipo | $228.59 | ||||
| Costo Directo | $1,539.26 |