| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CAR-1-07-6-6 | Señalamiento vertical SID-15 de 122 X 368 | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 22368 | SEÑALAMIENTO 122 X 368 | PZA | 1.000000 | $27,000.00 | $27,000.00 |
| Suma de Material | $27,000.00 | ||||
| Mano de Obra | |||||
| CUAD002 | CUADRILLA No 21 OF. ALBAÑIL + 1 AYTE + 0.05 CABO | JOR | 3.000000 | $505.48 | $1,516.44 |
| Suma de Mano de Obra | $1,516.44 | ||||
| Auxiliar | |||||
| 150. | CONCRETO DE F'c=150 KG/CM2, HECHO EN OBRA, T.M.A.=19MM, RESISTENCIA NORMAL | M3 | 0.050000 | $724.10 | $36.21 |
| Suma de Auxiliar | $36.21 | ||||
| Costo Directo | $28,552.65 |