| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CAR-1-04-82 | RIEGO DE SELLO CON MATERIAL TIPO 3E | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA | AGUA(MANEJO) | M3 | 0.600000 | $12.00 | $7.20 |
| ELABSELL | MATERIAL DE SELLO -3E | M3 | 1.000000 | $100.00 | $100.00 |
| Suma de Material | $107.20 | ||||
| Mano de Obra | |||||
| 2RT | CUADRILLA No 65 (2 RASTRILLEROS 1 CABO) | JOR | 0.002000 | $700.45 | $1.40 |
| 2P | CUADRILLA No 2 (2 PEONES) | JOR | 0.001000 | $389.24 | $0.39 |
| Suma de Mano de Obra | $1.79 | ||||
| Equipo | |||||
| EQMION | CAMION DE VOLTEO DE 7 M3 | hora | 0.675000 | $274.05 | $184.98 |
| EQBARR01 | BARREDORA FRONTAL | hora | 0.005000 | $114.52 | $0.57 |
| EQTANDEN | COMPACTADOR CATERPILLAR DOBLE RODILLO | hora | 0.050000 | $434.51 | $21.73 |
| Suma de Equipo | $207.28 | ||||
| Costo Directo | $316.27 |