| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| O-E-U-20 | PISO DE CONCRETO DE F'c=200 KG/CM2 DE 10 CM DE ESPESOR ACABADO PULIDO ,REFORZADO CON MALLA 6X6:6/6 .INCLUYE MATERIALES Y MANO DE OBRA. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO-03 | MALLA ELECTRO SOLDAD 6X6 6-6 . | M2 | 1.100000 | $13.44 | $14.78 |
| AGREGADO-003 | AGUA | M3 | 0.067000 | $40.00 | $2.68 |
| Suma de Material | $17.46 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 0.100000 | $876.53 | $87.65 |
| Suma de Mano de Obra | $87.65 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR | HERRAMIENTA MENOR | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| CONCRETO F-C=250 H/O | Concreto F'c=250 Kg/cm2 RN rev 10 cmAM 3/4" | M3 | 0.105000 | $981.74 | $103.08 |
| Suma de Auxiliar | $103.08 | ||||
| Costo Directo | $208.20 |