| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 331 | PISO DE CONCRETO DE 12 CMS DE ESPESOR EN ESTACIONAIENTO Y DRIVE TRUE ARMADO CON MALLA 6-6 10-10 | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MALLA 6X6-6/6 | MALLA ELECTRO SOLDAD 6X6 6-6 . | M2 | 1.100000 | $22.00 | $24.20 |
| CALZAS P/MALLA-ACERO | Calzas para malla o acero en pisos | PZA | 1.500000 | $0.95 | $1.43 |
| A GUA | AGUA | M3 | 0.067000 | $30.00 | $2.01 |
| Suma de Material | $27.64 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | JOR | 0.083330 | $859.49 | $71.62 |
| Suma de Mano de Obra | $71.62 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR. | HERRAMIENTA MENOR | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| CONCRETO F-C=250 H/O | Concreto F'c=250 Kg/cm2 RN rev 10 cmAM 3/4" | M3 | 0.125000 | $962.80 | $120.35 |
| Suma de Auxiliar | $120.35 | ||||
| Costo Directo | $219.61 |